Increased WIP = Increase in Lead Time

I've been viewing our Cumulative Flow Diagram and some interesting stats surrounding the work we are developing, our current flow rate and WIP.  Today I was able to see how increasing our WIP directly affects our Lead Time.


Our big spike is due to all the items being placed on the backlog (TODO) - although some of these may never be implemented more on this in the future! 

To summarize some of the information I can see (and you can't!):


Average Lead Time for any sized item from inception to live:
  • 35 days - 7 and 11 items in progress
  • 21 days - 2 and 5 items in progress
There are a number of things to note:
  • Variability in size has an impact on lead time - large items increase lead time.
  • Increase in Work in Progress decreases lead time.
 The above ties nicely in to Little's Law.